![]() |
![]() |
||||
|
|||||
|
|
|||||
![]() |
![]() |
||||
| Here is the area ready to receive new work. An existing sink was removed and an existing basement window (below grade) was blocked in. | |||||
![]() |
![]() |
||||
| I excavated the existing concrete floor to install new 4" and 2" PVC drains. Framing is complete, plumbing rough-in is complete. | |||||
![]() |
![]() |
||||
| Completed framing and electrical rough-in; Floor patched and leveled; Drywall installation in progress. | |||||
![]() |
![]() |
![]() |
|||
| The
finished bathroom with ceramic tile floor, pedestal sink, corner shower
stall, and toilet. The picture at right shows the new closet (mirror sliding doors) and the new laundry room access (bi-fold doors). |
|||||
![]() |
![]() |
![]() |
|||
| The next project will be the basement stairs. The new stairs will have rubber stair treads (full width of stair), painted stringers, knotty pine risers and walls, and a lighted railing. I'm planning to complete this project by Spring 2005. | |||||
BACK |
|||||